PROJECT DESCRIPTION: COMMERCIAL SERVER ROOM OUTLET INSTALLATION – SARASOTA, FL
We recently completed an electrical upgrade at a commercial newspaper facility in Sarasota, FL 34236. The project was initiated after a Fire Marshal inspection noted insufficient outlets in the server room, creating a compliance issue.
WHAT WE DID:
- Installed (2) new 4-bank outlet systems in the server room
- Ran dedicated circuits from the existing electrical panel to support the new outlets
- Ensured all wiring, conduit, and devices met NEC and local code requirements
- Coordinated installation to minimize disruption to daily operations
- Worked directly with onsite contact Jacob to confirm placement and functionality
THE RESULT:
The server room is now up to code with sufficient outlet capacity for current and future IT equipment. This upgrade resolved the inspection deficiency and provides the facility with a safer, more reliable power distribution system.
FREQUENTLY ASKED QUESTIONS
Why were additional outlets needed?
The Fire Marshal inspection revealed the server room did not meet outlet requirements for equipment load and safe distribution. Additional outlets prevent overloading and ensure compliance.
How many outlets were added?
We installed two new 4-bank outlet systems, providing eight additional receptacles dedicated to the server room.
Was downtime required during installation?
No major downtime was needed. We scheduled work around operations and coordinated with facility staff to ensure uninterrupted service.
Will this pass Fire Marshal re-inspection?
Yes. All work was completed to code and specifically addressed the cited inspection point. The facility is now ready for re-inspection.
Does Coharbor Electric handle other commercial code compliance issues?
Absolutely. We frequently assist businesses with electrical code upgrades, safety corrections, and compliance-related installations. Learn more about our Commercial Electrical Services.